THE BRIEF
- We were instructed to complete Ventilation Testing on this set of 9 flats in Hornchurch which is in the London Borough of Havering
- Each flat had a targets of 15 or above for the bathrooms and 30 or above for the kitchens
THE PROCESS
- After reviewing drawings, on site testing was ready to be completed. All calibrated equipment was setup in accordance to our strict procedures to ensure the most accurate result possible
THE RESULT
- Compliant
- All of the tests passed with no problems, meaning that their ducting was effective and their ventilation systems powerful