THE BRIEF

  • We were instructed to complete Domestic Air Pressure Tests on these new-build houses in Birmingham
  • The required target for these tests was ≤ 5 m³.h.m² @ 50pa

THE PROCESS

  • After reviewing drawings, on site testing was ready to be completed. All calibrated equipment was setup in accordance to our strict procedures to ensure the most accurate result possible

THE RESULT

≤ 5 m³.h.m² @ 50pa

Target

≤ 5 m³.h.m² @ 50pa

Target

3.59

Result

3.53

Result

PASS

PASS