THE BRIEF
THE PROCESS
THE RESULTS
≤ 5 m³.h.m² @ 50pa
Plot 1 Target
≤ 5 m³.h.m² @ 50pa
Plot 2 Target
≤ 5 m³.h.m² @ 50pa
Plot 3 Target
≤ 5 m³.h.m² @ 50pa
Plot 4 Target
≤ 5 m³.h.m² @ 50pa
Plot 5 Target
≤ 5 m³.h.m² @ 50pa
Plot 6 Target
≤ 5 m³.h.m² @ 50pa
Plot 7 Target
≤ 5 m³.h.m² @ 50pa
Plot 8 Target
≤ 5 m³.h.m² @ 50pa
Plot 9 Target
4.06
Plot 1 Result
4.08
Plot 2 Result
3.85
Plot 3 Result
4.15
Plot 10 Result
3.60
Plot 10 Result
3.79
Plot 10 Result
3.58
Plot 10 Result
3.56
Plot 10 Result
3.66
Plot 11 Result
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS